09 Mar 07 Work starts on Bar & Kitchen area in Phase 1 / More painting in Phase 2 / Phase 3 – The Tennis Court fence is finished
Phase One The builders have made much progress in this phase with the blockwork for the bar, kitchen and cool room going up in the past week. You can just make out the opening for the serving hatch of the kitchen in the photos. Alot of the ceiling boards are also up and the ceiling will be completed next week. The framework of the 1st floor is also now complete – this area will be kitted out in the coming weeks. Phase Two Decorating continues in this area. Phase Three The fence has been finished together with one or two pieces of snagging. The courts will now be left to settle until early April when they will be colour sprayed and kitted out with tennis equipment.
|